Communication bridge construction lowering.
About the project: As a result of inconsistencies on the construction site, it was necessary to decrease the height the part of built structure by several tens of centimeters.
For this purpose, the contractor decided to cut part of the columns and lower the bridge using hydraulic supports. The reinforcement bars were then connected using Terwa ALC connectors and the exposed part of the steel structure was re-concreted.
The entire operation took no more than one day and cost a very small part compared to the demolition and reconstruction of the bridge.